Vermont Agency of Transportation Project Development Process
Table of Contents
Transportation Planning Initiative - Selection of State System Projects
Selection of Town Highway Bridge Projects
Selection of Maintenance Projects
Bridge Deck Rehabilitation
Bridge Paint Program
Culvert Replacement Program
Guardrail Program
Maintenance and Capital Improvement to District Buildings ProgramSelection of Enhancement Projects
Selection of Interstate Bridge Projects
Selection of Paving Projects
Selection of Rail Projects
Selection of Airport Projects
Selection of Public Transit Projects
Selection of Rail Crossing Projects
Selection of Bicycle/Pedestrian Path ProjectsState System Projects Selected Through the Transportation Planning Initiative
Town Highway Bridge Projects
Maintenance Projects
Rail/Highway Crossing Projects
Enhancement Projects
Interstate Bridge Projects
Paving Projects
Bike Path and Park & Ride Projects
Rest AreasPurpose and Need
Information Collection
Local Concerns Meeting
Purpose and Need StatementProject Scoping
Resource Team Review
Prepare Alternatives with Footprint
Resource Agency Coordination
Alternatives Presentation Meeting
Alternative AcceptanceConceptual Design
Applicability
Definition
Content of Design Submittal
Approvals
Coordination
Submission
Environmental Determinations and Applications for Federal/State Permits502/Informational Hearing
Revisions to Plans
HearingNEPA Documentation (CE) Approval
CE Analysis Sheet
Section 106
Section 4(f)Act 250 Application Submittal (Part 1)
Preliminary Plan Development
Applicability
Definition
Run and Tie Centerlines
Subsurface Investigation
Contaminated Soils
Preliminary Plans Submittal
Utility Relocation Routes
Property Owner Visits
PermitsSemi-Final Plan Development
Applicability
Definition
Act 250 Submittal (Part 2)
Semi-Final Plans Submittal
Right-of-Way Plans Development
Reevaluation of the CE
Act 250 Permit Issuance
Authorization to Acquire Right-of-WayFinal Plan Development
Applicability
Definition
Final Plans Design Memo
Utility Agreements/Special Provisions
Railroad Agreements
Final Plans Submittal
Special Provisions
Contract Plans Submittal
Reevaluation of the CE
Authorization to Advertise for Receipt of BidsWaste and Borrow Areas
Staging Areas
Mitigation
Pre-construction Conference
Project Inspections During Construction
Change OrdersNotice
Impacts
Need for Administrative Intervention
Major Changes
Bulletin 3.5
Work Beyond Contract LimitsRight-of-Way Changes
Temporary Rights
Permanent AcquisitionsGeneral Permit 3-9001 for Stormwater Runoff from Construction Sites
Final InspectionAppendix A - Site Visit Checklist
Appendix B - CE Request Form Letter and CE Analysis Sheet
Appendix C - Public Participation
Introduction
Authorization to Proceed
Local Concerns Meeting
Alternatives Presentation Meeting
PDT Meeting
Property Owner Visits
SummaryAppendix D - Purpose and Need Statements
Appendix E - Evaluation Matrix
Appendix F - State and Federal Environmental Constraints
Vermont Environmental Laws and Regulations
Federal Environmental Laws and Regulations
Environmental Considerations in Project Development
Glossary
A List of State and Federal Permits and ApprovalsAppendix G - Hearing Procedures
Appendix H - CE Reevaluation Process