|
The
Bennington Bypass is divided into three major segments. The
Western Segment is constructed and was opened to traffic in
October of 2004; the Northern Segment began construction in 2007; the
Southern Segment is in the conceptual design stage with no
official construction schedule. The alignment of the new
highway was selected, in part, to minimize environmental
impacts. Wildlife crossings, a separate amphibian mitigation
site and a separate wetland mitigation
site have been implemented to offset potential impacts that
the construction of the highway may have on the environment.
WETLAND MITIGATION SITE
The Wetland
Mitigation Site, constructed as part of the Western Segment,
was built to mitigate anticipated wetland impacts for all
three segments of the initial (two-lane) Bypass. The
mitigation site, located on the east side of Bennington, is
called the Barney Brook Wetland Mitigation Site. It is 26.5
acres in size and is intended to mitigate for approximately
15.2 acres of impact for the entire project. The site was
constructed in 2000 and in 2001a five-year monitoring effort
began. Since its creation, the site continues to flourish.
Annual inspections have indicated that the site is
well-stabilized and vegetated. Along with well established
vegetation, various species of wildlife have been observed at
the site. Some of the species witnessed include: beaver,
red-winged blackbirds, green frogs, bull frogs, leopard frogs,
mallards, song sparrows, warblers, a green-backed heron, tree
swallows, a great-blue heron, Canadian geese. Deer tracks have
also been observed. The
five year monitoring period was completed in 2005. The report
concluded that the wetland was fully established and
functioning as intended.
|
 |
 |
|
BEAVER
CHEWINGS AT
BARNEY BROOK SITE |
Wildlife Crossing Under a
Lengthened Bridge |
Wildlife
crossings were also incorporated into the design and
construction of the Western Segment. This was accomplished by
lengthening two of the bridge structures over streams to allow
the passage of wildlife without having to compete with
vehicular traffic on the road above. In conjunction
with the University of Massachusetts at Amherst, VAOT is
conducting a wildlife crossing study in the vicinity of the
bypass to gauge the effectiveness of these structures.
The goal is
to evaluate how effective the lengthened bridge(s) act as wildlife passage
structure(s) and applying this knowledge to future projects so
that safety is increased for motorists and wildlife alike.
Data collection has been completed and a report is being
prepared by the University of Massachusetts at Amherst.
In the spring
of 1995, a herpetological study of the Northern and Southern
Segments identified areas of amphibian habitat along the
highway alignment which would be impacted by construction. A
man-made waterbody known as the Veteran’s Reservoir was
recognized as an amphibian habitat (specifically, as
reproduction habitat for ambystomid – a type of salamander).
The reservoir was once used to supply water to the Veteran’s
Home, but its use was discontinued, and the reservoir and
outlet structure fell into disrepair. Due to the pending
impacts on the reservoir by the highway, it was agreed to by
VAOT, FHWA and the various resource agencies to mitigate
impacted amphibian habitat at the Veteran’s Reservoir. The
mitigation area is being constructed as part of the
second contract of the Northern Segment which began
construction in April 2008 and will contain approximate 0.3 acres of
wetland and will include repairs to the outlet structure.
For more information
contact:
James Harris
Project Manager
123 Phyllis Lane
Bennington, VT 05201
Phone: (802) 447-
6425
Fax: (802) 447-2713
E-mail: James.Harris@state.vt.us
|