Bennington Bypass Main Page

Western Segment

Northern Segment

Southern Segment

Welcome Center
Project Archaeology
Project Environmental
Project Design Details
 
 
 
 
 
 
 
 
 
Bennington Bypass
The Northern Segment
 

Bennington Bypass
The Northern Segment
 

The Northern Segment, officially known as the Bennington NH 019-1(5) project begins at the US Route 7 systems interchange and proceeds southeasterly for approximately 3 miles to an interchange with Vermont Route 9, just east of downtown Bennington. This segment, in combination with the Western Segment, will constitute the bypass for Vermont Route 9 in the area.  

Construction of the first contract of the Northern Segment began in July 2007 and will span several years. A second contract was awarded in April 2008 with completion scheduled for 2010.  Another contract was advertised for bids in April 2009 and awarded shortly thereafter. This contract has a scheduled completion date of fall 2011. A final contract is scheduled to begin in, 2010.  Work for the Northern Segment includes the construction of a new two-lane highway, six new bridges, four of which are approximately 470 feet long, a new pedestrian overpass, a hiker underpass to access Bald Mountain and the Appalachian/Long Trail corridor, the reconstruction of the existing systems interchange, and the construction of the northern half of a new single-point diamond interchange with Vermont Route 9. Three major power transmission lines, each over 7,500 feet in length, were relocated in 2007 as part of this project. 

As part of this project, a significant amount of rock was removed from Exit 2 on US Route 7. This has been a safety concern for the Agency that was resolved through this effort. Rock excavated from the site is being utilized in various forms on the Northern Segment. The removal work is complete and the northbound ramps have been re-opened for use by the traveling public.  Also as part of this project, a significant amount of earth will need to be excavated and removed (wasted) from the alignment of the Northern Segment. Finding a location in the Bennington area to accept such a large quantity of material proved to be a challenge from environmental and cost perspectives. The Southern Segment highway alignment was identified as being both large enough to accept the additional earth and the highway profile of the proposed Southern Segment dictated that additional material would be needed to build the roadway to its desired elevation. As a result, the excess earthen material is being moved to sites along the future Southern Segment alignment and placed as engineered fills. This will be a cost saving measure for both the Northern and Southern Segments. 

Another interesting aspect of the Northern Segment is the identification of potential locations for a southwestern Vermont welcome center. In 1999, the Vermont Legislature instructed the Vermont Agency of Transportation to develop the site design of a possible welcome center in Bennington at the systems interchange of Routes US 7 and VT 279. This investigation is  complete, its conclusions accepted by Federal Highway Administration (FHWA) and the welcome center is expected to be built by the Office of Buildings and General Services (BGS) in conjunction with the construction of the Northern Segment of the Bypass. 

 

For more information contact:

James Harris
Project Manager
123 Phyllis Lane
Bennington, VT  05201

Phone:  (802) 447- 6425
Fax:       (802) 447-2713
E-mail:  James.Harris@state.vt.us

 

For more information contact:

James Harris
Project Manager
123
Phyllis Lane
Bennington, VT  05201

Phone:  (802) 447- 6425
Fax:       (802) 447-2713
E-mail:  James.Harris@state.vt.us



Email: 
Page Master regarding information or comments about this page

Last Modified:
Back to Top