RESULTS OF BIDS
 |
|
The following is a list of recent projects that have been let and the
Contractor who bid, along with their bid amounts. The list starts
with the low bidder and ends with the highest bidder.
*
Denotes change in Amount from As Read Bid to Confirmed Bid
**
For those projects with only a single bidder, Detailed Results of Bids
will not be
posted until after award, if award is made.
|
Note: To view Historic Bid
Results:
Historic Bid Results |
|
ALBURGH-ROUSES POINT BHF MEMB (24)(RE-ADVERTISED)
BIDS
OPENED ON: FRIDAY, FEBRUARY 3, 2012
|
|
Contractor |
Bid Amount As Read: |
Bid Amount Confirmed: |
|
Peckham Road Corporation |
$3,269,028.15 |
$3,269,028.15 |
|
Kubricky Construction Corporation |
$3,631,785.25 |
$3,631,785.25 |
|
The Lane Construction Corporation |
$4,294,806.80 |
$4,294,806.80 |
|
Luck Brothers, Inc. |
$4,754,838.76 |
$4,754,838.76 |
|
|
For
Detailed Results of Bids,
click here. |
|
BROOKFIELD IM 089-1 (59)
BIDS
OPENED ON: FRIDAY, JANUARY 20, 2012
|
|
Contractor |
Bid Amount As Read: |
Bid Amount Confirmed: |
|
S.D. Ireland Concrete Construction Corporation |
$435,812.85 |
$435,812.85 |
|
T Buck Construction |
$495,120.00 |
$495,120.00 |
|
A.L. St. Onge Contractor,
Inc. |
$496,668.17 |
$496,668.17 |
|
Miller Construction, Inc. |
$520,802.80 |
$520,802.80 |
|
Winterset, Inc. |
$578,477.15 |
$578,477.15 |
|
Cold River Bridges, LLC |
$634,091.50 |
$634,091.50 |
|
R.M. Piper, Inc. |
$672,922.50 |
$672,922.50 |
|
Parent Construction, inc. |
$726,174.90 |
$726,174.90 |
|
Northern Construction Service, LLC |
$799,181.90 |
$799,181.90 |
|
New England Infrastructure,
Inc. |
$1,245,624.00 |
$1,245,624.00 |
|
|
For
Detailed Results of Bids,
click here. |
|
BARTON-IRASBURG IM 091-3 (48) (RE-ADVERTISED)
BIDS
OPENED ON: FRIDAY, JANUARY 20, 2012
|
|
Contractor |
Bid Amount As Read: |
Bid Amount Confirmed: |
|
Frank W. Whitcomb
Construction Corporation |
$5,131,397.25 |
$5,131,397.25 |
|
Pike Industries, Inc. |
$5,624,843.50 |
$5,624,843.50 |
|
|
For
Detailed Results of Bids,
click here. |
|
NEWPORT CITY BRO 1449 (25)
BIDS
OPENED ON: FRIDAY, JANUARY 13, 2012
|
|
Contractor |
Bid Amount As Read: |
Bid Amount Confirmed: |
|
Reed & Reed, Inc. |
$5,192,093.50 |
$5,192,093.50 |
|
CCS Constructors, LLC |
$5,214,698.00 |
$5,214,698.00 |
|
A L St Onge Contractor, Inc. |
$5,599,998.15 |
$5,599,998.15 |
|
Northern Construction Service, LLC |
$5,639,009.50 |
$5,639,009.50 |
|
New England Infrastructure, Inc. |
$5,957,387.20 |
$5,957,387.20 |
|
Kubricky Construction Corporation |
$6,258,800.56 |
$6,258,800.56 |
|
The Lane Construction Corporation |
$6,449,548.00 |
$6,449,548.00 |
|
Winterset, Inc. |
$7,704,499.50 |
$7,704,499.50 |
|
JA McDonald, Inc. |
$8,248,970.00 |
$8,248,970.00 |
|
|
For
Detailed Results of Bids,
click here. |
|
For
questions or suggestions on our website please email us by
clicking
here. |
|
|
|